Insights and Analysis
AI-washing – when AI hype becomes a litigation risk
Incremental improvement in bankability, but not a complete solution: MOIT's proposed increase of Qc to 75% and extension of the applicable term to up to 15 years would enhance revenue visibility and support financing; however, core bankability concerns—particularly around payment security, dispatch risk, and fuel supply alignment—are likely to remain.
Policy balancing act between investor support and cost control: Vietnam is seeking to attract private LNG investment while avoiding over-contracting and excessive electricity costs, with the 75% Qc proposal representing a calibrated compromise rather than a full risk-allocation shift to offtakers.
A comprehensive package—combining enhanced Qc with payment and curtailment clarity, fuel contract alignment, targeted Government support (e.g., GGU), and pricing reform—is critical to make LNG to power projects truly bankable to international standards.
Vietnam is considering strengthening offtake assurances for LNG-to-power projects through proposed amendments to Decree 56 given lukewarm interest from sponsors and financiers with respect to the current framework. Policy discussions led by the MOIT indicate that the “Long-term Minimum Contract Quantity” (Qc) may be increased from 65% to 75%, alongside a potential extension of the applicable term from up to 10 years to as much as 15 years. These proposed changes are intended to enhance the bankability of LNG projects identified under the amended Power Development Plan VIII (PDP8), while balancing the risks of over-contracting and higher system costs for Electricity of Vietnam (EVN).
Under PDP8, Vietnam targets 22,524 MW of imported LNG power capacity by 2030 and 34,724 MW by 2035, with a long-term orientation toward co-firing or conversion to hydrogen by 2050. The plan identifies 21 LNG thermal power projects, including 15 projects scheduled for operation between 2025 and 2030 and six projects for the period from 2031 to 2035.
Policymakers view LNG as a flexible and dispatchable energy source that is critical for facilitating the integration of large-scale renewable energy and ensuring system reliability. However, LNG-fired generation remains significantly more expensive than many alternatives and is inherently exposed to global commodity price fluctuations and geopolitical risks since LNG represents an imported fuel source for Vietnam. During recent periods of market stress, electricity prices have reportedly surged to approximately VND5,000/kWh. This context has heightened the focus on designing regulatory mechanisms that both secure energy supply and maintain affordable tariffs.
Following the enactment of Electricity Law No. 61/2024/QH15, the Government issued Decree No. 56/2025/ND-CP on 3 March 2025 and Decree No. 100/2025/ND-CP on 8 May 2025 (amending Decree 56/2025/ND-CP) (collectively, Decree 56).
Decree 56 introduced two key mechanisms for LNG-to-power projects in an attempt to alleviate certain sponsor and lender concerns:
Currently, Qc is set at no less than 65% of a plant’s average power generation output (GO) during the loan repayment period, subject to a cap of 10 years from the Commercial Operation Date (COD). After this initial period, Qc levels or payment ratios under power purchase agreements (PPAs) revert to applicable laws and market rules.
GO is determined in accordance with Ministry of Industry and Trade (MOIT) regulations on generation charges and is incorporated into PPAs. Notably, Decree 56 limits eligibility to projects achieving COD on or before 31 December 2030, thereby leaving uncertainty for projects scheduled for commissioning thereafter.
Implementation of the Decree 56 framework is underway. The Nhon Trach 3 and 4 LNG power projects (1,624 MW) commenced operation and participation in the competitive electricity market on 1 January 2026. In addition, Phase 1 of the Hiep Phuoc LNG Power Plant has signed a PPA with EVN and entered the construction phase.
Notwithstanding these developments, the current Qc framework has elicited mixed feedback:
Lenders continue to emphasize the need for stronger take-or-pay features, enhanced payment security, and lender protections such as step-in rights.
MOIT, as the lead drafting authority, has conducted extensive consultations involving 16 ministries, agencies, and major energy stakeholders, including EVN, Petrovietnam, TKV, and LNG project developers1.
In its summary of stakeholder feedback, MOIT clarified that:
To inform potential adjustments, the National Electricity System and Market Operator (NSMO) and the Institute of Energy conducted modelling across multiple load scenarios using PDP8 data. Their analysis suggests that Qc levels of 80% or higher would likely result in systemic over-contracting across most scenarios, increasing cost burdens due to payments for unused contracted capacity.
Against this backdrop, MOIT has proposed increasing Qc to 75% as a balanced, targeted adjustment to strengthen investment signals while mitigating systemic risks. Market discussions also include extending the Qc duration to up to 15 years to better align with project financing tenors.
MOIT proposes increasing the Qc from 65% for 10 years to 75% for 15 years to strengthen investment signals and align with typical project financing tenors. This is a welcome adjustment that should improve revenue certainty. However, to achieve full bankability for LNG-to-power, the Qc enhancement must be accompanied by reforms that address dispatch risk, LNG fuel contract alignment, payment structures, and counterparty credit support.
Key outstanding issues include:
Interestingly, given EVN’s claim of instances of over contracting as a basis for maintaining Qc at 65%, it would be helpful for EVN to clarify where and how such over contracting has occurred in practice. With LNG to power operations currently limited, primarily to Nhon Trach 3 and 4, specific examples or data would strengthen this assertion and help distinguish LNG related over contracting from broader system wide contracting dynamics.
The market interprets EVN’s preference to retain Qc at 65% as an indication of sensitivity around payment obligations under PPAs. This underscores the need for stronger credit support and targeted Government backing to address counterparty risk and lender concerns. To mitigate payment risk and enhance bankability, a robust payment security package should be implemented, including:
Further, for strategic LNG‑to‑power chains, a Government Guarantee and Undertaking (GGU), aligned with Vietnam's precedent BOT framework for large power projects is recommended to bridge the gap between sponsor and lender expectations, on the one hand, and MOIT's position, on the other hand, which would cover: EVN payment obligations, change‑in‑law compensation, convertibility and transfer risks, and termination payments – recognizing the practical constraints on SOEs in pledging cash flows at levels typically required by international lenders.
Market feedback indicates that a minimum offtake level of 65–75% remains below investor expectations (often 85–90%). Without addressing this gap and the associated payment and credit protections (e.g., targeted GGU for priority projects), many LNG-to-power projects are likely to continue experiencing delays in their ability to obtain international project financing and commence construction.
The contemplated increase of Qc to 75%, with a longer applicability period, represents a careful policy balance: bolstering investment signals for LNG-to-power while avoiding the systemic cost risks associated with higher Qc levels. However, raising Qc alone will not resolve core bankability issues.
A more coherent package – including at least calibrated Qc, clear curtailment and payment mechanisms, alignment with LNG supply obligations, robust payment security (and targeted GGU for priority projects), and a flexible pricing framework —is needed to meet lender requirements. Decisions on the scope, duration, and applicability of the enhanced Qc framework will be decisive for Vietnam’s LNG-to-power development over the next decade.
Authored by David Harrison and Hai Ha.